As a Project Controls Manager of the Fresh Kills Landfill Leachate Mitigation project, responsible for instituting a change order management system, earn value reporting, and schedule controls
for a consent order driven project that stipulated 45 contractual intermediate milestones each carrying a penalty of $15, 000/day.