Project Controls Manager, International Technology Coporation (acquired by Shaw Group), Fresh Kills Landfill Leachate Mitigation project

START Date: 
July, 1990
END Date: 
April, 1994

As a Project Controls Manager of the Fresh Kills Landfill Leachate Mitigation project, responsible for instituting a change order management system, earn value reporting, and schedule controls
for a consent order driven project that stipulated 45 contractual intermediate milestones each carrying a penalty of $15, 000/day. All of the consent order milestones were met. Mr Mehta was Awarded National Quality Award from the IT corporation for effectively implementing effective project controls on this critical program.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
1000