Channel Tunnel Rail Link (CTRL) and Insurance Loss adjusting consultant

Planning Consultant, CCI Ltd, Halcrow, Union Railways, Channel Tunnel Rail Link (CTRL) and Insurance Loss adjusting consultant

START Date: 
September, 2005
END Date: 
April, 2006

I prepared an integrated completion and operational readiness programme for the final phase of the CTRL for URN and all stakeholders, encompassing the works and ensuring the buy in of all Stakeholders involved in operating the railway, Builder, Operators, Maintainer, Approving Authorities and the Client (3 days per week).  On the remaining days of the week I worked with a loss adjusting firm pre-dominatly on Business interruption claim at Seabank gas fired power station near Bristol.

Experience Hours (Planning & Scheduling): 
800
Experience Hours (Forensic Analysis): 
500