Section Engineer / Planner, Carillion, Canary Wharf Station

START Date: 
February, 1998
END Date: 
January, 2000

Section enginner and planner responsible for close out and handover of Canary Wharf Station on the Jubilee Line Extension

Site Enigneer, Carillion, Canary Wharf Station, Jubilee Line Extension

START Date: 
November, 1995
END Date: 
December, 1996

Site Engineer - Structures, Canary Wharf Station, Jubilee Line Extension.  Responsible for Concrete Slab construction at all levels of the Station