The Critical Path, Delay Analysis and “Windows” By Roger Gibson

The Critical Path, Delay Analysis and “Windows”

By Roger Gibson

Causation; Construction contracts; Delay; Design defects; Power stations; Remedial works

Doors & Window Installation

Installation

For windows that are not 'built-in' as work proceeds...

  • Install & Fix - By Area = 2.0 m2/hr
  • Install & Fix - By Girth = 4.0 m/hr

Mastic Pointing = 6.0 m/hr