Head of planning and reporting group

Head of planning and reporting group, AKKUYU NÜKLEER ANONİM ŞİRKETİ, Akkuyu nuclear power plant

START Date: 
May, 2014

The space of developing:

  • WBS of NPP AKKUYU Project description developing,
  • Basic planning and control procedure developing,
  • Directive schedule follow-up,
  • Licence schedule developing and follow-up on 1 and 2 level,
  • Integrated schedule of preparation period follow-up on level 2
  • Monthly project status-report preparation.
  • Separate chapters of Licensing plan preparation
Experience Hours (Planning & Scheduling): 
2700
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0