Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Revision of Columns Formwork from Wed, 2009-07-15 10:47

Rates include for fixing, cleaning and minor repair works etc, rates in m2/hr unless otherwise stated.

                   

Cross Sectional Area-->  Ne 0.2 m2 Exc 0.2 m2
Item Fix Strike Fix Strike
Kickers-Direct to slab (no/hr) 4.00 12.50 2.63 8.33
Kickers-Suspended (no/hr) 2.08 12.50 1.39 8.33

  Square Sides-Timber Clamped and Propped                     
  Column Height--->    2 - 3 m    3 - 4 m
Item   Fix Strike Fix Strike
Cross Section 0.00 - 0.05 m2 1.35 2.70 1.67 3.57
  0.05 - 0.10 m2 1.69 3.45 1.82 3.85
  0.10 - 0.20 m2 1.82 4.00 2.33 4.55
  0.20 - 0.40 m2 2.04 4.55 2.44 5.00
  exc 0.40 m2 2.33 5.26 2.50 5.88
 