Installation Sequences
Industrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete.
Installation Periods
Size Of Kitchen |
Are of Kitchen |
Installation Time |
100 people |
50 m2 |
3 weeks |
500 people |
150 m2 |
5 weeks |
1,000 people |
275 m2 |
8 weeks |
For individual installations...
Ovens, friers and large mixers etc = 1 man day per item
Sinks, bain maries, washers etc = 2 man days per item