Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Revision of Kitchen Installations from Sat, 2009-03-07 14:48

Installation Sequences

Industrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete. 

Installation Periods 

Size Of Kitchen

Are of Kitchen

Installation Time

100 people

50 m2

3 weeks

500 people

150 m2

5 weeks

1,000 people

275 m2

8 weeks

 For individual installations...

 Ovens, friers and large mixers etc = 1 man day per item

Sinks, bain maries, washers etc = 2 man days per item


 

 

Market Place

No results found... (try selecting a different content filter)