Ground Excavation Rates (m3/hr):

 

Ground Type Bucket Bulk Works Basements Trenches Small & Deep
Sand/Soil 0.3m3 8.7 8.0 7.1 8.4>
  0.4m3 28.5 15.4 25.0 10.0
  0.5m3 50.0 20.0 28.6 13.3
Gravel 0.3m3 7.1 6.9 6.1 4.5
  0.4m3 25.9 14.3 22.2 8.7
  0.5m3 40.0 18.1 28.6 11.1
Clay/Chalk 0.3m3 7.1 6.5 6.1 4.1
  0.4m3 25.0 13.3 22.2 8.3
  0.5m3 40.0 16.7 28.6 10.5
V.Difficult 0.3m3 6.1 5.9 5.4 4.1
  0.4m3 22.2 11.8 20.0 7.7
  0.5m3 28.6 11.8 20.0 6.7