Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Planning & Scheduling Engineer, WorleyParsons, Integrated Gas Development (IGD) Project – Das Island

START Date: 
November, 2009
END Date: 
November, 2011

 

B. Integrated Gas Development (IGD) Project – Das IslandThe project involves both offshore and onshore works with building new jetties, jackets, breakwater and flaring facilities on the offshore part and building most of the facilities to be built on the newly reclaimed area of land which will house the 3 trains for Gas dehydration and Compression interlinked with the existing utilities.