3D / 4D Planning Engineer, Trojan Constructions, Akoya by Damac (446 Villas )

START Date: 
January, 2014
  • Creating tender, baseline and target program for different projects.
  • Preparing the Weekly and Monthly Progress reports For the Different Projects.
  • Monitor and Review the work progress in the site.
  • Weekly update, review and analyse of schedules and identify the critical and sub-critical causes of delay.
  • Attend weekly progress meeting with the Clients and Consultants.  
  • Review and continuously monitor the subcontractors program and make sure it will not cause any delay.
  • Prepare and monitor the procurement schedules in compliance with the construction schedule.
  • Prepare and update extension of time claims (Change in the approved MEP drawings, delay in Municipality Inspection and delay in Civil Defence preliminary approval Claim.)
  • Advice the project manager/project engineer of any slippage of progress and corrective actions to be taken.