Planning Manager, CCC (Consolidated Contractors Company), Nile Corniche Project

START Date: 
April, 2012

Planning Manager

Reporting to the Project Director, main accountabilities are:

-       Review of contractor schedules, updating and status reporting to the Director of the Committee on same.

-       Provide recommendations when actual progress deviates from scheduled progress.

-       Conduct analysis of alternatives and options in the programming of the works to allow “what if” considerations where market fluctuations, implementation of changes, and/or unanticipated events impact the design and construction schedule.

-       Oversee and monitor the development of database programs being implemented to meet the Project requirements.

-       Oversee preparation of Master Schedule and Details Schedules for construction including review of contractor schedules, updating and status reporting to the Director of the Committee on same.

-       Preparing the Master Contract programme (Clause 14).

-       Preparing a revised programme (Clause 14.2).

-       Preparing a claim programme (impact analysis, cause and effect)

-       Liaise with the Engineer and Sub contractors concerning the progress.