Senior Planning Enginner, Harris Pye Power Services, Newport Energy from Waste Project

START Date: 
January, 2020
  • Newport EFW Project

Construction of Energy from waste Facility, this is an EPC form of Contract. The works include the Engineering, procurement and construction of all infrastructure, Process Plants (boiler, ACC, Turbine, Flue Gas Treatment Plant & BOPs) Process buildings, and commissioning of the facilities.

 

Responsibilities

·        Newport EFW Project

 

Construction of Energy from waste Facility, this is an EPC form of Contract. The works include the Engineering, procurement and construction of all infrastructure, Process Plants (boiler, ACC, Turbine, Flue Gas Treatment Plant & BOPs) Process buildings, and commissioning of the facilities.

 

Responsibilities

·           Working on Tender schedule for the wining work team to support tender documents for a potential project.

Appraised and integrated subcontractor programmes into the master programme

  • Engaged actively to develop Milestone projection, delay, float analysis and actively monitor programme risks and communicate any changes to all stakeholders.
  • Helped Identify budgetary and programme issues that need to be addressed with the client to ensure satisfaction and ensure the agreed key performance indicators, as agreed with the client, are met

 

  • Attend schedule meetings and liaising with subcontractors and client to agreed reporting timescales with internal and external stakeholders to demonstrate progress.

 

  • Organise collaboration session with all Engineering Package leads to ensure they are actively involved in the scheduling of activities and to ensure they take ownership of activities on the master schedule.
  • Attending regular progress meeting to report on progress and risk and to provide controls support to the project team.
  • Measured and Track performance of all live Site works and provide forecast on final labour, delivery dates by producing S-Curves for project monthly report.
  • Actively involved in developing iterative engineering approach to ensure live construction proceed & mitigate Engineering delay caused by Covid 19.
  • Producing look-ahead Schedule for Engineering, procurement and construction teams.
  • Develop Master information release tracker to ensure all engineering blockers are dealt with in a timely manner.

 

  • Develop various scenario for Covid impact on project key

Milestones

  • Develop Phasing plan and daily tracker of all current site activities.
  • Organise and co-ordinate daily site works meeting.
  • Develop and manage Site works blocker tracker to ensure works continuity on site.
Experience Hours (Planning & Scheduling): 
11400
Experience Hours (Cost Management): 
5300
Experience Hours (Forensic Analysis): 
8000