Director of Planning and Scheduling, Riverside Group -Six Flags China, Six Flags-China Haiyan-Riverside

START Date: 
November, 2016
END Date: 
September, 2017

Six Flags China-Riverside

      1 Overall schedule for six flag and riverside (Show, Ride, Facade, Area Development, Facility(first phase and second phase infrastructure ,vacuum pre-loading treatment, piling work, foundation, structure, MEP, decoration and facade)

      2 41 Nos. Ride Delivery Schedule (Contract Award, Design information submittal and approval, Piling drawings, Shop Drawing,  Piling, embedded part delivery, Foundation, structure, ride steel column delivery, ride track delivery, Ride Installation, vehicle delivery, commissioning, CSEI  Review ,handover to operation)

     3 Theme park and Water Park schedule incl. authority, engineering, procurement, construction, commissioning, handover, operation, delivery, payment, information, HR and marketing.

     4 Waterpark Summary Schedule incl engineering

     5 Attend 41 Nos. Ride Contract Bidding and Tendering Meeting, Review delivery schedule and work scope.

     6 GC contract review, Develop milestones for GC and subcontractor

     7 Contract award schedule progress review, third party agency for ride transport, customs and internal transport, payment.

     8 Specification study and format modified, system and procedure development for planning and scheduling, change order, material replacement.

     9 Forrec SD,DD,LDI IFC and shop drawings study