Cost & planning Engineer, MMJV & Water Corporation, Alkimos WWTP
START Date:
November, 2008
END Date:
March, 2010 · Worked with a multidiscipline team of contractors to deliver a much needed waste water system for the residents of Alkimos.
· Involved in cost control for non-directs and engineering costs. Monitored project activity data for accuracy and efficiency.
· I was also the monthly reporting Coordinator, I worked with the contractors to get accurate costings and progress information which I compiled into a report for the client.
Experience Hours (Planning & Scheduling):
2000
Experience Hours (Cost Management):
1000
Experience Hours (Forensic Analysis):
100 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: