Estimator and scheduler, EPCM-psi, Oil Refinery Turnarounds

START Date: 
November, 2012

Estimator for 2013 Shutdown/Turnaround using EPCM-PSI’s Component Based Estimating method for all equipment involved in the refinery.  Scheduling is done using EPCM-PSI’s Float Based Prioritization Method, all of which is done in P6.  I created a manpower projection spreadsheet for a 2013 Turnaround based on 10-30% estimates