Lead Planner, Three Streams Engineering, Foster Creek Phase F- SAGD
START Date:
October, 2010
END Date:
January, 2012 Three Streams Engineering Nov 2010-Jan 2012
Planning and Scheduling Lead Calgary, AB
Built and maintained resource loaded detailed CPM Engineering/Procurement schedules using P6 for Cenovus Oil Sands expansions. Projects were:
- Foster Creek Phase G CAD$ 340 Million
- Brackish Water System CAD$ 207 Million
- Prepared and published weekly reports on engineering EWP/CWP and Procurement ETAs for variance analysis and mitigation plans if necessary
- Prepared and maintained models for progress measurement, productivity factors and earned value calculations.
- Compiled and presented projects dashboard reports and schedule variance analysis reports
- Forecasted Man-hours Estimate to Complete, based on earned value measurements, productivity trends, and thorough activity analysis
- Participated in recurring review meetings with the clients, namely Cenovus and Nexen, representing Project Controls and supporting Project Managers
- Integrated data from cost control tools with Primavera schedules to derive valuable analysis
- Directed planning team efforts through guidance, mentoring and skill developing
- Company:
- Industry:
- Job Role:
- Project:
- Region: