SITE ENGINEER, KANETHARA PROJECT PVT LTD, Ship Building
START Date:
February, 2009
END Date:
June, 2010
Planning & project monitoring covering, Co-ordination with yard & site activities:- · Piping fabrication, erection, pressure test (hydrostatic & pneumatic) · Mechanical clearance, punch list. · Planning for a month, daily checking of work, progress, planning as per drawing. · Prepare weekly progress & Yard man-hours productivity report for management review. · Prepare manpower histogram area wise by weekly. · Weekly meeting with client. · Prepare and update daily, weekly, monthly, and close out report. · Prepare and attend projects meeting (weekly, bi-weekly and monthly). |
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: