Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Planning Engineer, Doosan Babcock, (various projects)

START Date: 
January, 2009
END Date: 
October, 2011

 

Jan 2009 – Oct 2011

Doosan Power Systems (Doosan Babcock)

Planning Engineer – GSK Montrose

Key Responsibilities:

  • Using MS Project to continually develop and maintain the site Master Schedule for all projects on site
  • Create construction programmes using Primavera P6 and Microsoft Project 2007 for individual projects incorporating contractors detailed scope of works and programmes
  • Create weekly dashboard reports to show project KPI’s, weekly achievements, risks and concerns, a weekly lookahead and an ‘S’ curve to show planned project percent complete against actual
  • Create project estimates using Isometric Drawings
  • Hold interactive planning meetings for all projects to obtain ‘Buy In’ from all involved
  • Provide resource information / histogram and pro-actively identify resolutions to any limitations (re-sequencing activities, extended hours, sufficient warning etc)
  • Visually inspecting progress made using Isometric drawings and reporting back to the project engineer prior to updating the programme
  • Receive sub-contractor updates and any additional works to allow maintenance of overall project programmes
  • Walk projects to allow maintenance of individual construction programmes
  • Liaising with the site manager, project engineers and supervisors throughout the process and making adjustments to the project as necessary
  • Ensure communication of schedule requirements between all parties involved as regularly as is deemed necessary and giving enough time to highlight critical activities