Assistant Manager - Project Controls, Eiffage Construction Metallique, Ofon Phase II

START Date: 
January, 2008
END Date: 
December, 2012

Eiffage Oil & Gas Construction Company, Aveon Offshore Facility, Rumuolumeni, Port Harcourt

(Project: Total E & P- OFON Phase II Project)

Offshore Planning /Project Controller (July. 2011-Till Date):

  • Review the implementation time schedules which are periodically issued by the Contractor for each sub-project regarding match with the actual progress and achievement of the planned progress.
  • Develop and maintain the Scheduler’s own implementation time schedules for the purpose of establishing a systematic and consistent estimate of the percentages of completion for each sub-project. Broken down into the disciplines Engineering, Procurement, Construction & Erection and Commissioning. Present the progress as planned and achieved by the Contractor in form of tables and S-curves for each sub-project and also for the total project (weighted average).
  • Monitor and verify Contractor’s work progress in all areas for the purpose of progress payments and assist the Project/Site Manager in issuing the payment certificates with all necessary backup and evidence. The primary progress assessment in the field is however done by the discipline engineers.
  • Maintain records for all contract variations whether implicitly or explicitly agreed between Contractor and Employer.
  • Receive and implement instructions as given by the Project Manager.
  • Cooperate in all activities with the PE Site team in accordance with the instructions of the Project Manager/Site Manager.