Planning Engineer, CSSI- France based in Algeria. , Building Works

START Date: 
June, 2006

(i)      Preparing and Establishment of Detailed “Work Break Down structure” with Synchronizing Project activity to developing Project planning.  

(ii)     Preparing of Level-1, Level-2, Level-3, Level-4 Project Schedule and monitoring the Project accordingly with weekly and monthly basis.

(iii)    To ensure the schedule is in lined with Contract, developed and implemented the Project Baseline schedule and progress monitoring.

(iv)   Preparing the Project planning with resource allocation, this leads to generate Project cash flow and manpower Histogram.

(v)    To review Engineering documentation schedule and deliverable dates for schedule impacts.

(vi)   To ensure that all interfaces and short term critical activities are reviewed.

(vii)  Assist the Package Manager in preparing weekly and monthly progress reports with Planed, Forecast and Actual Progress status including S-Curve.

(viii)Prepare resource, work KPIs to track the Project.

(ix)   Preparation of look ahead schedule and review the same with each discipline lead personnel’s and publish in weekly and monthly report.

(x)    Progress evaluation with weekly and Monthly basis and certification.

(xi)   Preparation of recovery plans during the delays in project and lineup the schedule with original baseline.

(xii)  Preparing Project Planning Documentations.

(xiii)Preparing monthly project-closing reports as additional input for management and estimation.

(xiv)Calculate the Productivity factor against Budgeted Vs actual.

Preparing Manpower, Machineries Load on Monthly/Yearly basis, Look Ahead Schedule on Fortnightly, Monthly, Three Month basis