Role: Lead Planner Project: VVB / Morgan Sindall JV. Cooling The Tube Project - Green Park.

Project: Crossrail - (C405) Paddington Project - VVB/Skanska Rashleigh Weatherfoil JV (MEP), Skanska, Byrne Bros.

 

Responsibilities:

  • Produce, update and monitor the main project programme in Primavera complete with all documentation, contract milestones and key-dates, labour and logic linked, together with accompanying narrative, and reports on Critical Path.
  • The programme to be broken out in a Work Breakdown Structure, reflecting the phases of work, e.g. Design (where applicable), Procurement, Construction & Installation, Test & Commissioning, Handover. The programme is also typically loaded with both labour and materials, as tendered.
  • Update of M&E Works in the 4 Weekly Look-ahead programme with Primavera and occasionally Xcel. Updating Percentage Complete, forecasting completion dates, updating data dates, and labour loading and levelling. By tracking instructions from clients from time of issue to completion, construct, monitor, progress and report on other programmes as necessary using Primavera P6 or, if required, Excel. Where necessary record Early Warnings and the impact on the programme.
  • Attend, and report in the weekly Team Progress Meetings, weekly coordinated planning meetings between various contractors on projects, like Skanska, Costain and Byrnes Bros. Working within the NEC contracts delivering programmes with Compensation Event Notices, identifying approved, pending or disallowed CE’s. Cost incurred, with or without lead times and where applicable with programme impact.