Senior Planner or Senior Planning Engineer, Daewoo E & C, Degassing Station Facilities Project

START Date: 
May, 2003

Job Objective                                                     

 

Over ten (11) years of Project Management and Control Experienced in Construction and Plant(EPC Projects); Various Constructional (i.e; Military Facilities, Residential, Educational and High Rise

Building) and Plant (i.e; Power and Chemical) projects as Planning Engineer (Scheduler).

 

Summary of Experience                                              

 

Years of Experience: 11 years , Discipline/Specialty: Planning Engineering(Scheduler)

 

Participated in Degassing Station Facilities Project, Iraqand experience in project control(Scheduling, Analysis of schedule)

 

Participated in KNPC Halon Phase-Out Project of Kuwait and experience in project control(Scheduling, Analysis of schedule and Claim analyze)

 

Participated in Raipur 660MWx 2Units Coal Firing Power Plan Project of India and experience in project control(Scheduling,Analysis of schedule and Claim analyze).

 

Participated in New Songdo City Project(High Rise Building(50F),International School Project) of Korea and experienced in analysis& forecasting of schedule based on PV,EV,SV and SPI data construction & design and analysis claim and preparation of recommendation report for the client

 

Participated in U.S Army and Air Force Construction Projects(Housing, School, Barracks and JOC) in Korea and experienced in estimation & preparation of schedule for proposal projects and after award, preparation of project schedule, updating and analysis of schedule to minimize time impact

 

 

Career Highlights                                                    

 

Degassing Station Facilities Project, Iraq (ENI)

Senior Planning Engineer / Project Management Team / Daewoo Engineering & Construction

2014~Current /EPC Lump-Sum/ Contract Amount: $500,000,000 / Petrochemical Plant

 

Job Description:

  • Development of WBS, Activities, Duration Estimation, Standard Logic
  • Preparation Level3 EPC Project Schedule using Primavera 8.2
  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Development of Progress Measurement System
  • Preparation of EVMS
  • Preparation of Weekly, Monthly Report

 

Halon Phase-Out Project, Kuwait (KNPC)

Senior Planning Engineer / Project Management Team / Hanwha Engineering & Construction

2012 – 2013 / EPC Lump-Sum / $280,000,000 / Petrochemical Plant

Job Description:

  • Monitor EPC project progress using Primavera 8.0(Identify critical & near critical activities, Analysis and Forecasting of delay activities)
  • Preparation and Revision of EPC Project Master Schedule  
  • Preparation of Weekly and Monthly Reports.
  • Preparation of Schedule Early Warning Reports.
  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Development and Update of Progress Measurement System
  • Preparation of Recovery Plan due to Project delays
  • Preparation of Schedule Analysis for Claim Report

 

Petrochemical Quay2 Project,Saudi Arabia(SABIC)

Senior Planning Engineer / / Project Constrol Management Team / Hanwha Engineering & Construction 2012 – 2012 / EPC Lump-Sum / Contract Amount: $300,000,000 / Petrochemical Plant

 

  • Development of WBS, Activities, Duration Estimation, Standard Logic
  • Preparation Level3 EPC Project Schedule using Primavera 7.0
  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Setting Up Progress Measurement System
  • Setting Up and Weekly, Monthly Report

 

Raipur 660MWx 2Units Coal Firing Power Plan Project , India (GMR)

Senior Planning Engineer / / Project Constrol Management Team / Doosan Heavy Industries & Construction

2010 – 2011 / EPC Lump-Sum / Contract Amount: $1,000,000,000 / Power Plant

Job Description:

  • Monitor EPC project progress using Primavera software 7.0(Identify critical & near critical activities, Analysis and Forecasting of delay activities)
  • Preparation and Revision of EPC Project Master Schedule  
  • Preparation of Weekly and Monthly Reports.
  • Preparation of Schedule Early Warning Reports.
  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Development and Update of Progress Measurement System
  • Preparation of Recovery Plan due to Project delays
  • Preparation of Schedule Analysis for Claim Report

 

Central Park I (48F, Mix-Use Residential), Korea (Gale International)

Senior Planning Engineer / New Songdo City Project Control Team / Parsons Brinckerhoff Asia (for Client)

2008 – 2010 / Turn-Key / Contract Amount: $110,000,000 / High-Rise Building

 

Job Description:

  • Reviewing and Analysis of Project Construction Schedule using Primavera software6.0
  • Preparation and Management of Master Project Schedule
  • Preparation of Monthly & Weekly report for Client,
  • Analysis and Forecasting of schedule based on PV,EV,SV and SPI data ,
  • Analysis claim and preparation of recommendation report for the client.

 

New Songdo City International School , Korea (Gale International)

Planning Engineer / New Songdo City Project Control Team / Parsons Brinckerhoff Asia (for Client)

2007 – 2008 / Turn-Key / Contract Amount: $100,000,000 / International School

 

Job Description:

  • Reviewing and Analysis of Project Construction Schedule using Primavera software5.0
  • Preparation and Management of Master Project Schedule
  • Preparation of Monthly & Weekly report for Client,
  • Analysis and Forecasting of schedule based on PV,EV,SV and SPI data ,
  • Analysis claim and preparation of recommendation report for the client.

 

JOC (Job Order Contractor), Area I&II and Air Force Base, Korea(FED,US Army Corps of Engineers)

Scheduler & Estimator / FED Team / Poonglim Engineering & Construction

2006 – 2007 / Cost Fee / $30,000,000 / Renovation of Upgrading Buildings

Job Description:

  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Preparation of Project schedule & Estimation Sheet for Proposal
  • Preparation and Management of Submittals and Transmittals
  • Managementdelivery of off-shore materials
  • Prepare monthly invoice data for the periodical monthly invoicing

 

Interim Elementary School, Pyeong Taek, CP Humphrey ,Korea (FED,US Army Corps of Engineers)

Scheduler & Estimator / FED Team / Poonglim Engineering & Construction

2005 – 2006 / Turn-Key / $10,000,000 / International School

Job Description:

  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Preparation of Project schedule & Estimation Sheet for Proposal
  • Preparation and Management of Submittals and Transmittals
  • Managementdelivery of off-shore materials
  • Prepare monthly invoice data for the periodical monthly invoicing

 

Multi Story Family Housing (60units), Yongsan Garrison, Korea(FED,US Army Corps of Engineers)

Archtectural Engineer & Scheduler / FED Team / Pumyang Engineering & Construction

2003 – 2004 / Turn-Key / Contract Amount: $35,000,000 / Housing Building

Job Description:

  • Preparation and Update of S-Curve for Project Progress, Manpower and Equipment
  • Preparation of Recovery Plan due to Project delays
  • Prepare monthly invoice data for the periodical monthly invoicing to the client
  • Management and Controlling the process of works phases (Preparatory Inspection, Initial

Inspection)

  • Preparation and Management of Submittals and Transmittals
  • Management and Updated QCS System( Quality Control System)
Experience Hours (Planning & Scheduling): 
25000
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
3000