Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Supervising Engineer, COWI, Drainage and Wastewater Management Project

START Date: 
November, 2001
END Date: 
January, 2003

Resposible for Quality Supervision, Progress Montoring & Reporting of a small Earthen Dam, 18 kms long Open Canal Drainage System, 8 kms long Sewerage System, 5 kms long Black Topped Road, Staff Quarter, Office cum Laboratory Building, Workshop, Garage, Parking area and a Wastewater Treatment Plant with 2 Anaerobic Concrete Ponds (Total Volume of 2 ponds: 7500 m3), 9 Aerobic Ponds (Total Volume of 9 ponds: 12,000 m3), Emergency Holding Tank (Volume: 780 m3) and Sludge Drying Beds (4000 m2).