Area Planning Manager, first united general contracting, Social Security Buiding
§ Develop detailed implementation plans and control procedures, enabling the analysis of contractor's, subcontractor's, manufacturer's and suppliers basic activities, including significant milestones through a work breakdown structure.
§ Organize the correct resources to take advantage of the available physical resources by leading/providing guidance to management and subcontractors. That will result in their doing effective timely work.
§ Implement, maintain and update a computerized progress control system which enables the monitoring and follow up planned/actual physical progress. This is done through use of a computerized software system such as spread sheet or primavera.
§ Comparison of the execution program, actual achievements and forecasts by monitoring , measuring or controlling the project work to find out how progress differ from plan in time to initiate corrective action with a consequent need to change resources. This is done through the use of critical path network, bar charts, progress curves, histograms and follow-up tables.
§ Prompt identification of delay, and where necessary actions required implementing corrective measures to recover any slippage.
§ Create new performance measurements plan if the performance deviates from the contract execution program to the point where the original plan can no longer be an effective basis for control.
§ Evaluate claims for time extension or disruption.
§ Reporting to the management on the work progress during the entire duration of the contract
- Construction
§ I have a great experience in Concrete and finishing work as a site engineer.
Professional Development
- Bachelor Degree in Civil Engineering-2005
Shoubra Faculty of Engineering(CAIRO) - Zagazic University
Graduated with grade: Good
My graduated project in Structure
Graduated with grade: Excellent
- CertifiedPMP #1444158 (Project Management Professional) - Aug.2011
Project Management Institute (USA)
- Various courses supplement my extensive hands-on my field experience:-
· Cost Engineering(online) American University in Cairo (Feb ~ May 2012) Egypt.
· Primavera P3, P6 & Advanced Toolsin Primavera Training Center (2008) Egypt.
· PMP Preparation ExamPrimavera Training Center (2008) Egypt.
· Access 2007MS-Office Center (2008) Kuwait.
· Auto Cadin Autodesk Training Center (2004) Egypt.
· OSHAConstruction Safety (2008) Kuwait.