Construction Project Planner, Galliford Try (Infrastructure Division), Network Rail Enhanced Security Measures
START Date:
January, 2012
- Used Primavera P6 to drive the project schedule and the engineering teams forward
- Conducted risk analysis for the various manageable projects across UK sites
- Maintained the planning filing system, participated in planning management control audits and acted as a key client interface for planning queries from the client
- Monitored and tracked progress of project and prepared 3 week look ahead programmes
- Prepared extensive reports to communicate progress status to all stakeholders
- Discussed project’s progress in management meetings with at WBS levels