Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Claims Analysis Planner, AMEC, Longannet Power Station - FGD

START Date: 
August, 2007
END Date: 
November, 2007

I spent four months assisting on a claim for the project. This included the production of a P3 programme which visualised the historical data collected in the analysis of many drawings, documents and the contract. Utilising my extensive knowledge of Earned Value allowed me to clearly analyse data and S-curve’s, ensuring I was fully prepared for discussions with the project manager and confident presenting to the client. I also often progressed the program actuals using P5 and updated the expended man hours on a weekly basis.