Freelance Senior Planner, Van Oord via Minstrell Recruitment, Liverpool 2 Container Berth

START Date: 
March, 2014

March 2014 – date - Ross Planning contract for Van Oord via Minstrell Recruitment – Liverpool 2 Container Berth, analysis in P6, ChainLink, comment & updating

Analysis of Bam Nuttall P6 programme for JV partner Van Oord for new container berth, using past marine experience. Also using ChainLink time-chainage and provide a high-level report on the effect of current piling delays, nominally on a day per week basis after initial input. Work started comparing Issue 8 with previous issues, then roughly monthly updates.

New programme for WP5 channel dredging linking to Issue 11 – part of the arisings are to be delivered for fill behind the new quay.