Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Principle Projects Planner, UGL Resources, LYNAS RARE EARTHS PROJECT – Design, Procure, Construct, Commission of Advanced Rare Earths materials plant project in Malaysia.

START Date: 
January, 2010
END Date: 
March, 2011

Projects Planner,1/2010 to 3/2011

Development of fully integrated Design, Procure and construction schedule.

Selected Accomplishments:

Implemented data process to take UGL Estimate values as Design engineering progressed into Procurement and Construction schedules. This included adding the schedule coding in reverse back into estimating system and 3D design models.

Implementation of Rare Earths Piping database related to Process flow diagrams, drawing register, schedule ID’s because of New Technology in piping installation processes for Rare earths product and changes in piping specifications.

Experience Hours (Planning & Scheduling): 
450
Experience Hours (Cost Management): 
100