Planner, ACC, %26 Oil %26 Gas Projects 2) Buildings 3) Infrastructure

START Date: 
October, 2006
  • Responsible in the preparation and submittal of master programmeon a hierarchicalbasis (WBS) and in logical sequence, identified the critical path using planning tool software to ensure timely completion and resolution of outstanding issues.
  • Preparation of Manpower and Equipment Histogram to plan for site requirements.
  • Ensure that all project phases, including design, construction, contractual requirements, engineering activities, procurement items, material and equipment deliveries, are included and embedded in the program.
  • Calculate & Prepare the project weighted factors based on cost loaded program recorded on agreed, quantifiable and measurable percentage to develop the project cash flow statement.
  • Preparation of material procurements and shop drawing schedule considering the material required dates and delivery dates and delivery lead times.
  • Review overall project status with the Project Control team and Project Management and recommend corrective action where necessary.
  • Prepare the weekly and Monthly Progress Reports updating the progress percentage (graphical representation shown in S-curve) for Submission to the consultant/client.
  • Alert the Site Management for delays observed in the ongoing works.
  • Review variation order for extension of time, delay impact and budget enhancements.
  • Monitor Daily Progress Reportsand Regular site visits.
  • Ensure effective communications is maintained with the Operations Team.