Development of level 1, level 2 and level 3 integrated master schedule based on CAPEX. Portfolio planning and forecasting resource requirements for future projects. Planning and controlling of multi-disciplinary engineering related projects. Resource loading the project schedule to generate s curves and histograms Integration of contractors schedule into the overall project plan. Updating the project schedule and measuring it against baseline schedule. Schedule variance analysis. Weekly progress updates and reporting of delays and deviation. Generating reports on planned vs. actual work. Monthly look head activities reports.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500