Senior Scheduler/Planner – Environmental, Statutory Approvals & Stakeholder Sub-Project, Orario Services Pty Ltd, APLNG Coal Seam Gas Brisbane
START Date:
April, 2011
END Date:
April, 2012 APLNG Coal Seam Gas Brisbane, Australia (Apr 2011 – Apr 2012) Scheduler/Planner – Environmental, Statutory Approvals & Stakeholder Sub-Project
- Responsible for development of the level 4 schedule encompassing the statutory and regulatory permit and approval process.
- Directed the design and implementation of a fully integrated program of schedules encompassing the requirements of design packages and land access liaison with 3 levels of government and local land owners to facilitate property access and environmental approvals
- Development of a progress measurement and schedule methodology capable of operating across EPBC, CG, EA, LGA and Tenement approvals, to provide integration with the program requirements for onsite construction access