Sr. Planning Engineer, Saudi Binladin Group (Public Buildings & Airport Division), Building Construction

START Date: 
June, 2011

Following are some of the tasks during this period, for King Abdullah Financial District (KAFD) Project with contract value of 14 Billion Saudi Riyal.

Provide the major milestones to the sub-contractors based on Master Plan to prepare the Working Schedules.

Reviewing the Working Schedules for Façade & Elevators Works submitted by sub-contractors.

Arrange meetings with sub-contractors, design team and site construction staff to resolve the issues related to Façade & Elevators Works and the development of Baseline Schedule.

Prepare the Cash Flow histogram for forecast.

Produce S Curve & Resource Histogram (Manpower, Equipment, Cost).

Prepare the Earned Value Matrices and update the same for Earned Value Analysis.

Provide weekly, fortnightly & monthly look-ahead schedule to the site construction managers.

Prepare the Impacted Schedule (P6) for EOT claims.

Develop recovery plans & revise the plan on internal and client requirements.

Update the Master Schedule (P6) monthly & prepare monthly progress reports.