Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Manager, London Underground Limited, Station Upgrade on Numerous Station

START Date: 
March, 2002
END Date: 
May, 2004

Project Manager - London Underground

Responsible for delivering the station upgrade requirements of the PPP contract (appendix 14 & 15)

Carrying out the duties of the planning supervisor as required by the Construction (Design & Management) Regulations 1994;
Contract Administration of the NEC Contract;
Producing detailed cost plans, phasing expenditure and cash flow over the term of each project;
Gaining funding against planned budget and delivery of project benefits;
Liaising with the Portfolio Scoping and Initiation Manager to determine and agree the project requirements, so as to ensure that the business objectives are met;
Interrogating the programme and risk to ensure achievability;
Ensuring a safe system of work is in place.

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
0