How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture:

How to assign resource / resource loading / make resource plan in Primavera P6

In Primavera P6, after finish creating the schedule, you may need to assign resource to activity to make the resource plan.

I will show you how to do it.

Let say you have a schedule like in below picture:

How does Resource Shift Calendar in Primavera P6 work?

In Primavera P6 -> Resources window -> Units & Prices tab, there is a selection box called Shift Calendar