START Date:
February, 2008
-Assist in the drawing up of tender, high-level & level 5 detailed construction and engineering schedules encompassing mechanical, structural and piping disciplines.
-These schedules were drawn up on an hourly basis and monitored accordingly via percentage complete and man-power/hours. Once complete the schedule was baselined and reported upon to the client via daily and weekly reports “S-curves” and interface meetings.
-Co-ordination of procurement and delivery of material to site.