ROLANDO LACAP

First Name: 
ROLANDO
Last Name: 
LACAP

PERSONAL DATA:

NATIONALITY               Australian

SEX                             Male
CIVIL STATUS               Married
 

EDUCATIONAL ATTAINMENT:
ELEMENTARY               Masantol Central School     1971 – 1977
HIGH SCHOOL               Pampanga Colleges          1977 – 1981
COLLEGE                      University of the Assumption     1981 – 1986
                  COURSE     Bachelor of Science in Civil Engineering

SPECIAL SKILLS:

  1. Primavera Specialist / Scheduling Professional / CPM Analyst – P3.1, P5.0, P6.1 – 6.8
  2. SAP Operator
  3.  Cost Engineer / Earned Value Training / Cost to Completion Projections
  4. Interactive Planning Specialist using IAP Tools Netpoint.
  5. Quantity Measurements / Performance Measurements Tracking
  6. Holder of Defense NV1 Security Clearance

COMPUTER SKILLS:

     Project Management Tools: Primavera 5.0, 6.0 & 3.1, MS Project – 2007.
     Database Management Programs: VB for Excel (Macro coding & Recording)
     Spread Sheet Application: Advance Knowledge of MS-Excel with all most all the relevant functions.
     MS Office: Advance Knowledge of MS-Word & MS-Power Point.

WORKING EXPERIENCE:

POSITION TITLE            :   Sr. Project Control Engineer / Interactive Planning  Specialist

NAME OF COMPANY       :    Jacobs / SKM

DATE                           :    03 Feb 2014 to Present

 RECENT PROJECT EXPERIENC

Client                           : BHP Billiton

Projects Undertaken     : Electric Slag Furnace Rebuild Project (DPS)

 Client                           : BHP Billiton

Projects Undertaken     : Electric Slag Furnace Rebuild Project (SPS)

Client                           : SANTOS

Projects Undertaken     : IPS Greenfield Project

 

KEY ACHIEVEMENTS:

Performs schedule development, maintenance, and monitoring activities.

Conduct Interactive planning sessions Australia Wide as per Project Manager’s request.

Update project hours and cost status using company’s project control software

Identifies schedule-associated cost trends for management attention.

KPI Dashboarding and preparation of monthly progress report for presentation to company stakeholders and clients.

Identification of critical path tasks and report against these.

Delay analysis, review and request extension of time (EOT) if needed

Identification of long lead time tasks, in conjunction with all other areas and report against these.

Identified delays and corresponding impact to Master Program and/or Target Program.

Assisted in the determination of schedule impact that results from contract variations.

OTHER TRAINING:

Netpoint or Interactive Planning (IAP) training took Place in Jacobs Houston Office on July 14 to 25 2014.

The Aim of the Training is to have a Netpoint Guru or Netpoint Practice Leader in Australia.

Netpoint is an high level scheduling tool that enables schedules to be manipulated in a workshop environment:

A full wall electronic interactive scheduling tool when used in conjunction with an interactive hardware device.

Allows the facilitator to create and manipulate a live schedule with associated logic

Provides instantaneous feedback to stake holders and attendees of changes in networked activities

When complete, the output of the session can be imported directly into Primavera P6.

Allows for easy and real time “What If” scenarios to be run with real time resource (or cost) histogram review.

 

POSITION TITLE            :           Lead Planner

NAME OF COMPANY        :           Sinclair Knight Merz (SKM)

DATE                            :           23 July 2012 to 02 Feb 2014

 

RECENT PROJECT EXPERIENCE:

Client                           : BHP Billiton

Projects Undertaken     : Olympic Dam - Process Plant Upgrade

Client                           : Iron Road

Projects Undertaken     : Central Eyre Iron Project Stage 2

 Central Eyre Iron Project Stage 3

Client                           : Flinders Port

Projects Undertaken     : FACT Crane Procurement, Fabrication, Installation and Commissioning

KEY ACHIEVEMENTS:

  • Performs schedule development, maintenance, and monitoring activities.
  • Ensures work is completed as scheduled
  • Identifies schedule-associated cost trends for management attention.
  • Preparation of s-curves, production curves and schedule overviews.
    • Identification of critical path tasks and report against these.
  • Identification of long lead time tasks, in conjunction with all other areas and report against these.
  • Identified delays and corresponding impact to Master Program and/or Target Program.
  • Assisted in the determination of schedule impact that results from contract variations.



     POSITION TITLE     :     Sr. Planning Engineer
     NAME OF COMPANY     :     Abi Group Pty. Ltd.
     DATE               :     August 20, 2009 to 31 May 2012


     PROJECTS UNDERTAKEN:
CLIENT           : South Australia Water
PROJECT          : Adelaide Desalination Project (Adelaide Aqua)
PROJECT AMOUNT     : AUD 1.8B
PROJECT SITE REFERENCE: www.adelaideaqua.com

          
     KEY RESPONSIBILITIES

     Develop, Mature and Control the Detailed Construction
Schedule
     Monitoring & Reporting Progress Against Schedule on a
weekly basis
     Reconciliation with Status of Master Program & Target
Program on a weekly basis
     Communication of Detailed Schedule status with
Procurement team
     Preparation of Internal / External Program Reports
     CORE ACCOUNTABILITIES:

     Compliance with Time Management Plan, Planning / Scheduling procedures and forms
     Promote a Safety culture
     Assist the Principal Planner as required
     Assist with preparation of internal and external schedule reports
     Lock the Procurement Baseline in alignment with the signed-off version of the Target Program ‘Required On Site’ dates
     Develop, mature and status the Construction detailed schedules
     Monitor and report progress weekly against Construction Baseline to Construction Team
     Preparation of s-curves, production curves and schedule overviews
     Assist with identification of key milestones and report against these
     Assist with identification of critical path tasks and report against these
     Assist with identification long lead time tasks, in conjunction with all other areas and report against these
     Monitor and Status the Process Design Schedule on a weekly basis
     Identify delays and corresponding impact to Master Program and/or Target Program
     Assist in the determination of schedule impact that result from contract variations
     Meet regularly when required by the Principal Planner with project management to review the detailed schedules.


     PROJECT DESCRIPTION:

When completed the Adelaide Desalination Plant (ADP) will supply 50GL/PA of potable water, which is about 20% of Adelaide’s total water requirements. The ADP will be one of the most advanced Salt Water Reverse Osmosis (SWRO) desalination plants in the world, utilizing a combination of water technologies not used anywhere else in Australia in turn making it the most energy efficient plant in use.

The plant has also been designed so that its output capacity can be easily doubled to 100GL/PA, should the need arise.

AdelaideAqua is a consortium of 4 companies who together will Design, Construct, Operate and Maintain the Adelaide Desalination Plant.

The work is covered by 2 Contracts, 1 for D&C and 1 for O&M.

The D&C Contract is being undertaken by an unincorporated joint venture consisting of Abigroup, Acciona Agua & McConnell Dowell.

The O&M Contract is with a company called AdelaideAqua Pty Ltd, which is owned by Acciona Agua and United Utilities (UU Australia Holdings Pty Ltd).

During construction there will be a very close working relationship between the D&C and O&M teams to ensure that the plant is “built right” achieving the required water quality and quantities at the lowest cost.

The total project is worth in excess of $1.8 billiion and involves extensive earthworks, piling, tunneling (2 tunnels), building and plant fit out activities to be completed in a very tight timeframe, delivering First Water by Dec 2010 (this is not the plant completion date!).

     POSITION TITLE     :     Planning Engineer
     NAME OF COMPANY     :     John Holland Group Pty. Ltd.
     ADDRESS          :     1000 Ann St. Fortitude Valley,
Queensland, 4006
     DATE               :     October 24, 2008 to July 30, 2009


     PROJECTS UNDERTAKEN:
CONTRACT NO.      : Q008-001
CLIENT           : PORTS CORPORATION OF QUEENSLAND (PCQ)
PROJECT          : ABBOT PONT X25 EXPANSION PROJECT
PROJECT AMOUNT     : U.S.$ 45M

     PROJECT DESCRIPTION:

The Abbot Point Coal Terminal (APCT) is owned by Ports Corporation of Queensland (PCQ) and operated by Abbot Point Bulk coal (APB)

X25 is an expansion stage to increase overall throughput at APCT to a nominal 25 million tonnes per annum by the construction of Dump Station 2 which is a new installation of equipment including rail beams, steel hoppers and vibrating feeder systems into the existing rail receival building and vault beside the existing Dump station 1. Replacement of some existing equipment which services the whole rail receival system is included.

Construction of the In loading System to allow Dump station 2 to service both Bund 1 and Bund 2. This is achieved with four new conveyors and associated equipment.

Stockyard Upgrade Increased capacities for the conveyors servicing Bund 1. This is achieved by speeding up existing conveyors using new drives.

Out loading Upgrade, A higher ship loading capacity from the existing system. This is generally achieved by speeding up existing conveyors with new drives and drive pulleys. In certain cases, the existing conveyor belts and idlers are also replaced with wider belts to achieve the higher capacity.


     JOB PROFILE:

     Review current status of both Engineering and Procurement for the Project
     Prepare a revised detailed Level 3 control schedule (Primavera P3) incorporating the physical status and all change orders. This was part of the integrated schedule and network for the EPC contract.
     Prepare Shutdown and Commissioning Schedule
     Assist the cost engineer in the revised control budget
     Revise the drawing and document register used at level 5 to ensure all were identified and entered for the basis of scope
     Review and advise on actions required for recovery on procurement schedules from the contractors, to meet delivery at site for the on site required dates.
     Prepare scenarios to show the impact of Design Change Notices to the completion of the Project. Revise Work Breakdown Structure.
     Updating the progress with existing schedule and Prepare revise schedules
     Material Management
     Preparation of weekly and monthly progress report.
     Conduct weekly internal review meeting as per the ISO requirement.
     Maintaining all the records and drawings as per ISO procedure.
     Allocating material and manpower.
     Preparation of bill materials
     Preparation of Quantity survey & bill for work performed.
     Estimating the impacts on construction schedule to the Client / Consultant.
     To discuss with client and / Consultant to issue the change order to contract.
     Reconciliation of materials and machinery’s.
     Preparation of Job Close-Out Report.


     POSITION TITLE     :     Sr. Project Control / Sr. Planning Engineer
     NAME OF COMPANY     :     R.H. Al – Marri & Sons Co.
     ADDRESS          :     P.O. Box 1, Abqaiq, 31992 K.S.A.
     DATE               :     March 2000 September 2, 2008

     JOB PROFILE:

     Responsible for all Project Controls and support to the Project Director’s for the co-ordination and development of bids for Projects.
     Prepare the Master Control Schedule for each. Negotiate with all clients the scope, unit prices/lump sums and Milestones
     Manage all Cost, Planning & Document Control Dept’s
     Develop of the detailed budget/cost allocations, control schedules (Primavera P3, P5 and P6)
     Identify and Analyze Project Risk and Recommend Management/solutions
     Discuss Initial Plan to Higher Management thru Power Point Presentation
     Monitor Field Planners and Update the Progress
     Develop and implemented procedures for Cost, Planning and Document Control for compliance with the contract and also for our own internal controls
     Prepare Shut down Schedule.
     Review and revise all reports, evaluate/amend and take any necessary actions required
     Prepare and negotiate any variations relating to the client. Negotiate the scope, terms and conditions of the larger Sub-contracts and all claims from sub contractors
     Prepare all reports for the Project Directors.


     ROJECTS UNDERTAKEN:

CONTRACT NO.           : 6600017980
PROJECT     : PIPELINE REHABILITATION PROJECT
PHASE V
CLIENT     : SAUDI ARAMCO PIPELINES PROJECT
DEPARTMENT (CROSS COUNTRY
PIPELINE PROJECTS DIVISION)
PROJECT AMOUNT     : U.S.$ 44M


     Replacement of 46” to 48” Dia. Oil & Gas Pipeline
From Safaniyah Plant to Juaymah Tank Farm

CONTRACT NO.           : 6000014977
PROJECT     : KHURSANIYAH PIPELINES AND
COMMUNICATION PROJECT
CLIENT               : SAUDI ARAMCO KHURSANIYAH
                     MAINTAIN POTENTIAL DEPARTMENT.
PROJECT AMOUNT          : U.S.$ 93M
PROJECT REFERENCE SITE          :
http://www.gulfoilandgas.com/webpro1/MAIN/Ma
innews.asp?id=1852

Construction of 19 Water Injection Drill Sites and 1 Interface Manifolds
•     Scope Includes Fabrication, X-Ray, Internal & External FBE Coating of 8” to 16” Carbon Steel Pipes
•     Installation / Welding, X-Ray, Internal & External FBE coating of 8” Flowline
•     Installation / Welding, X-Ray, Internal & External Coating of 16” Water Injection Header
•     Installation / Welding, X-Ray, Internal & External coating of 16” buried water injection lateral
Construction of 6 Water Supply & Utility Drill Sites & 2 Interface
Manifolds
•     Scope Includes Fabrication, X-Ray, Internal & External FBE Coating of 8” to 16” Carbon Steel Pipes
•     Installation of 8 Sand Trap
•     Installation / Welding, X-Ray, Internal & External FBE coating of 8” Flowline
•     Installation / Welding, X-Ray, Internal & External Coating of 16” Water Supply Header
•     Installation / Welding, X-Ray, Internal & External coating of 16” buried water supply lateral
•     Backfilling, Fencing & Installation Pipe Rack of Interface Manifolds
•     Installation / Welding of Manifolds Associated Pipings
•     Installation of Scraping Facilites




Construction of 27 Oil Drill Sites, 4 Remote Manifolds & 1 Interface
Manifold
•     Scope Includes Fabrication, X-Ray, of 8” to 16” Carbon Steel Pipes
•     Installation / Welding, X-Ray of 8” Flowline
•     Installation / Welding, X-Ray of 12” Production Header and 10”
Test Line header
•     Installation / Welding, X-Ray of 12” Lateral to Interface
Manifolds
•     Installation of Scraping Facilites & Associated Pipings
Construction of 52 RTU Buildings inside the Drilling Island
•     Site Development
•     Design, Estimation and Construction of Reinforced Concrete Wall & Roofing
•     Design and construction of 6 Layered Water Proofing of RTU Buildings
•     Design and Construction of Raised Floor System to facilitate Cable Ducts
•     Design and Construction of Reinforced concrete Pipeline Anchors
•     Design and construction of Air Conditioning Duct System

CONTRACT NO.           : 6600012402
PROJECT     : PIPELINE REHABILITATION PROJECT
PHASE IV
CLIENT     : SAUDI ARAMCO PIPELINES PROJECT
DEPARTMENT (CROSS COUNTRY
PIPELINE PROJECTS DIVISION)
PROJECT AMOUNT     : U.S.$ 40M

     Replacement & Reconditioning of 42” to 48” Dia. Oil & Gas Pipeline
From Abqaiq Plant to Berri Gas Plant

CONTRACT NO.           : 64000044676
PROJECT     : QATIF MAINTAIN POTENTIAL PROJECT
CLIENT               : SAUDI ARAMCO QATIF MAINTAIN
POTENTIAL PROJECT DIVISION
PROJECT AMOUNT     : U.S.$ 70M

PROJECT REFERENCE SITE     : http://www.saudiaramco.com/irj/portal/anonymous?favlnk=%2FSaudiAramcoPub...

     Construction of 12 Oil Drill Sites
•     Scope Includes Fabrication, X-Ray, of 8” to 16” Carbon Steel Pipes
•     Installation / Welding, X-Ray of 8” Flowline
•     Installation / Welding, X-Ray of 12” Production Header and 10”
Test Line header
     Construction of 16 Water Injection Drill sites
•     Scope Includes Fabrication, X-Ray, Internal & External FBE Coating of 8” to 16” Carbon Steel Pipes
•     Installation / Welding, X-Ray, Internal & External FBE coating of 8” Flowline
•     Installation / Welding, X-Ray, Internal & External Coating of 16” Water Injection Header
•     Installation / Welding, X-Ray, Internal & External coating of 16” buried water injection lateral

     Construction of 28 RTU Buildings
•     Site Development
•     Design, Estimation and Construction of Reinforced Concrete Wall & Roofing
•     Design and construction of 6 Layered Water Proofing of RTU Buildings
•     Design and Construction of Raised Floor System to facilitate Cable Ducts
•     Design and Construction of Reinforced concrete Pipeline Anchors
•     Design and construction of Air Conditioning Duct System

     Laying of Fiber Optic Cables
•     Laying of 60 Km Fiber Optic Cables from Drill Site RTU to Control Room
•     Construction of Duct Banks
•     Termination at RTU and control room
     Reconditioning of Existing Water Injection Lines.
•     Cold Cutting of Existing Water Injection Lines
•     Mechanical Cleaning
•     Internal Cement Lining of Existing Pipeline
•     Welding and X-Ray

     INVOLVED IN THE PREPARATION OF TENDER SCHEDULE OF THE FOLLOWING SAUDI ARAMCO FLAGSHIP PROJECTS.
     Manifa Water Supply System – U.S. $ 2.65B
http://www.rigzone.com/NEWS/article.asp?a_id=69539
     Qassim Crude Oil Pipeline – U.S. $ 16M
http://www.rhmsons.com.sa/projects.php

     POSITION TITLE     :     Planning / Cost Engineer
     NAME OF COMPANY     :      Tonka Construction
Clark Special Economic Zone, Clarkfield, Pampanga
     DATE               :      February, 1998 to February, 2000

     JOB PROFILE:

     Responsible for preparing revised Level 3 network & Master Control
Schedule
     Liase with Sub Contractors Planning Engineers, for establishing their
Schedules and reports required to control their own scope
     Validate all schedules upon submission for baseline, approve all
Subsequent progress/updates
     Prepare Trend and forecast reports, Weekly and Monthly reports for Management
     Recommend Management solutions to the management

     PROJECTS UNDERTAKEN:

     Construction of Fire Lane Roads at Expo Filipino Clark. – U.S.$ 1M
CLIENT: Department of Public Works and Highways
•     Construction of 8 Km Concrete Pavement Inside the Expo Filipino
     Construction / Widening of J. Abad Santos Avenue at Clark Special Economic Zone, Clark field Pampanga. – U.S. $ 2M
CLIENT: Clark Development Corporation (CDC)
FUNDED BY: Bases Conversion Authority (BCDA)
•     Removal of Existing Concrete Curb and Gutter and Bicycle lane
•     Construction of 3.5 meter Concrete Pavement
•     Construction of Box culverts
     Construction of VIP Parking at Expo Filipino Clark. – U.S. $ 1M
CLIENT: Department of Public Works and Highways
•     Site Development
•     Construction of Asphalt Pavement and enter islands
     Construction / Rehabilitation of Four Storey Medical Facility Building of Former Clark Air Force Base. U.S. $ 5M
CLIENT: Clark Development Corporation (CDC)
FUNDED BY: Bases Conversion Authority (BCDA)
•     Demolition of Existing Structures
•     Construction of 5 Storey East Wing Building
•     Rehabilitation of Existing 5 Storey Building


     Construction of Protective Dike at Clark Field. – U.S. $ 4M
•     Construction of 1 Km Reinforced Concrete Slope Protection works resting on Reinforced Concrete Piles and Gabions
     Construction of Package 1, FVR Mega Dike, San Fernando, Pampanga – Bacolor Section. U.S. $ 10M
•     Construction of 3 Km Reinforced Concrete Slope Protection works resting on Reinforced Concrete Piles and Gabions
•     Construction of Gabion Spur Dikes

     POSITION TITLE     :     Planning Engineer
     NAME OF COMPANY     :      AIC CONSTRUCTION CORPORATION
Goldhill Condominium, Greenhills, San Juan, Metro Manila
     DATE               :      March, 1994 to January, 1998

     JOB PROFILE:

     Engaged to develop and update detailed networks, schedules (Open Plan) & estimate for the upgrade, installation and commissioning of systems
     Responsible for Project Controls of both Planning and Cost departments for the Engineering, Procurement, Fabrication & Construction
     Carry out risk analysis on both schedules and Budgets.
     Update budget with actual incurred, forecast, cash flow and escalation rates
     Update schedules with physical progress and man-hour expenditure to show all trends, status, forecast & prepare scenarios
     Evaluate all bids and revised Control Budgets/Schedules submitted by contractors

     POSITION TITLE     :     Project Engineer
     NAME OF COMPANY     :      AIC CONSTRUCTION CORPORATION
Goldhill Condominium, Greenhills, San Juan, Metro Manila
     DATE               :      November, 1992 to February, 1994

     JOB PROFILE:

     Actively involve in Project Estimation during Tender Stage.
     Supervise On-Going Project in Terms of Quality and Workmanship.
     Build an effective team highly motivated towards the achievement of goals
     Provide mentoring, training & coaching to develop & guide employees
     Undertake formal & informal employee career development activities to ensure business units have the skills & capabilities required to deliver operational & manufacturing excellence outcomes
     Manage performance of direct reports including: setting of annual goals, reviewing development needs & carrying out regular reviews

     PROJECTS UNDERTAKEN:

     Dredging and Construction of Pasig Potrero River, Pampanga, Philippines – U.S. $ 0.5M
•     Desilting of Pasig – Potrero River which is affected by the eruption of Mt. Pinatubo Volcano Eruption.
     Construction of 5 Storey Rich Mak Building, Mindanao Avenue, Pasig City, Philippines – U.S. $ 3M
•     Design and Construction of 5 Storey Building Owned by Former Congressman Rodolfo Bacani of 4th District Manila
     Construction of Protective Dike Between Lawin Mountain and Vega Hill. - U.S. $ 2M
•     Construction of Reinforced Concrete Slope Protection Works to Protect the Town of Zambales from Lahar Flow caused by the Eruption of Mt. Pinatubo Volcano
     Construction of Sabutan – Maguyam Road. Cavite City, Philippines – U.S. $ 2M
•     Construction of 14 Km Concrete Pavement Road
     Construction of Roadways and Utilities @ Navotas Fishport Complex, Navotas City, Philippines – U.S. $ 6M
•     Construction of Concrete Pavement Road
•     Construction of Port and 150 Stalls Public Markets
     Construction of El Nido – Lamoro – New Ibajay – San Fernando Road and Bridges. El Nido, Palawan, Philippines – Funded by the Asian Development Bank (ADB) Under Second Palawan Integrated Area Development Project (SPIADP) – U.S. $ 12M
•     Construction of 65 Km Access Road
•     Construction of 18 Reinforced Concrete Girder Bridge with an average Span of 60 Meters.
•     Construction of Reinforced Concrete Over Flow Bridge
     Dredging of Tublijon River Control. Davao City Philippines – U.S. $3M
•     Deepening and Widening of Existing River Bed
     Construction of Tabaco Fishport, Albay City, Bicol, Philippines
•     Pile Driving with crane on Barge
•     Design and Construction of Reinforced Concrete Slab
•     Design and Construction of 100 Stalls Public Market
     Construction of 3 km Irrigation Canal, Sto. Thomas, Pangasinan, Philippines
     Construction of Blumentrit Interceptor. Flood Control Project under Department of Public Works and Highways.

     POSITION TITLE     :     Project Engineer
     NAME OF COMPANY     :      MRT CONSTRUCTION
Jaena St., Pilar Village, San Fernando, Pampanga
     DATE               :      March, 1990 to October, 1992

     JOB PROFILE:

     Proactively contribute to business planning activities
     Deploy business plan through key units to align behaviour & focus effort & resources on critical activities
     Ensure policies, procedures & training is deployed effectively to drive delivery performance & operational efficiency & quality

     PROJECTS UNDERTAKEN:

     Construction / Asphalting of Manila North Road, San Fernando – Angeles City Section, Pampanga, Philippines
     Construction of San Fernando North West Road, San Fernando, Pampanga, Philippines
     Construction of San Jose Gymnasium, Nueva Ecija, Philippines – U.S. $ 1M
     Construction of 3 Storey San Ricardo National High School – U.S. $1.5M

     POSITION TITLE     :     Statistician I
     NAME OF COMPANY     :      Department of Public Works & Highways
Regional Office No. 3, San Fernando, Pampanga
     DATE               :      June, 1988 to December, 1989

     POSITION TITLE     :     General Construction Foreman
     NAME OF COMPANY     :      Department of Public Works & Highways
Regional Office No. 3, San Fernando, Pampanga
     DATE               :      February, 1987 to May, 1988


     PROJECTS UNDERTAKEN:

     Construction of Ninoy Aquino Boulevard.
     Construction of Tibag – San Isidro RCDG Bridge
     Construction of Marimla Bridge
     Construction of Cabanatuan Circumferential Road.
     Construction of Ninoy Aquino Highway, Arayat – San Simon Section.
     Construction of 4 Class rooms Pantabangan Elementary School
 

Professional Since: 
Mar-2000 (24.2 yrs experience)
Oldest experience: 
Aug 2009 (14.7 yrs experience, WARNING: 9.4 years variance with Professional Since)
Years Experience: 
45