5 Ways to Manage with Fewer Resources

2 replies [Last post]
Emily Foster
User offline. Last seen 1 year 47 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

No one wants to have to manage with fewer resources, but project teams are being squeezed all the time. Here are 5 Ways to manage with fewer resources http://ow.ly/sUkVn

Replies

Patrick Weaver
User offline. Last seen 4 days 20 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

More smoke and mirrors. The simple fact is, if you don’t have enough resources and management is doing its job to the best of its ability the work takes longer.

The linked blogs first option is ‘fast track where you can’.  Fast tracking overlaps phases that would normally be done sequentially.

Overlapping phases that would normally be done at different time means you need double the resources – you need enough resources to work on both phases at the same time but the problem is you don’t have enough resources to work on the current phase. Therefore you have twice as much work not being done!

The only useful advice is the last point – ‘don’t pretend it is OK’

For more on accelerating project work see: http://www.mosaicprojects.com.au/WhitePapers/WP1059_Schedule_Compression.pdf