Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activities Relations

2 replies [Last post]
Jenny Ingco
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear Schedulers,

I have WBS and the all activities in it are FS relations so, each one should start dierect behaind the processor is finish. But what happend I have gab now beteen two activities 20 days as far as the relation is FS. So, any idea why that's happinig?

 

Thank you all

Replies

Frederic Fasquelle
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Hi Hanson,

This gap could also be created by some predecessors not marked as "completed" and linked in FS to your current.
You could also have a look inside your Primavera log report, in chapter "Errors".

Regards

Ronald Winter
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Hanson,

This gap is probably due to the activity’s calendar.  Look for a vacation period.  Otherwise, look for lag values in the relationships.  Good luck!