Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Schedule progress agrument

No replies
Amir Pezeshk
User offline. Last seen 13 years 18 weeks ago. Offline
Joined: 5 Dec 2011
Posts: 14
Groups: None

Let's say in a complex construction project, contractor claims that he has completed 80% of the work but the inspector say he has done only 60%.  How can you check which one in correct by Primavera?  I am not asking to go EVM issue.  Is this really possible?