resorce assignnment effective date

2 replies [Last post]
kumar s
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
Dear All,

can you guide me for the below mentioned query..

i have assigned the resources of the last year(2008)project.
since the limit (max units/time) for the last project is set for ex.60h/h.
now dor the present project i hace to change it to 40h/h.
now i have 2 options .
either i can edit the limit in the already available units(whose effective date is jan 2008.
the other option is i can add one more unit and set the limit(with effcetive date as july2010)
so now when i level the resources p6 will take how many resources as available.
ie it will consider only the resorces of 2010 (with 40h/h)or it will take 2008 resources also(60h/h).

i think my question is clear.


thank you.....

Replies

Rodel Marasigan
User offline. Last seen 22 weeks 18 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
kumar,
P6 recognise new max time/unit for new resource assigned as long as the activity date fall higher or equal to date specified on new max time/unit. You can show the column of max unit/time on resource tab to check at the same time.
kumar s
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
can any body please reply to my query guys...