Schedule with SS relationships only??

1 reply [Last post]
Salman Ahmed
User offline. Last seen 15 years 2 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Dear all,

1.Is it right and logical to prepare a complete schedule using SS (start to start) relations only.

2.If yes..will there be any problem to the resources loaded.


Thank you all in advance.

Replies

Rodel Marasigan
User offline. Last seen 23 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Not a good practice and not advisable. You might end up of multiple open end activities.