Drive activity dates

2 replies [Last post]
Jash Sales
User offline. Last seen 13 years 33 weeks ago. Offline
Joined: 8 Dec 2009
Posts: 27
Groups: None
Dear All,

Could you please help me on how to un-check all resources with drive activity dates at one time in resource assignment? I have tried to highlights all resources and try to un-check but it could not work. any other way to do this except one by one?

Thanks,

Jake

Replies

Jash Sales
User offline. Last seen 13 years 33 weeks ago. Offline
Joined: 8 Dec 2009
Posts: 27
Groups: None
Many thanks Ian, I made the first option.
Ian Nicholson
User offline. Last seen 15 years 23 weeks ago. Offline
Joined: 29 Jan 2010
Posts: 42
Two options:

1) If you go to the activity assignments module, you can put that checkbox into a column, uncheck the first one and use Edit/Fill Down (CNTRL-E) to populate the rest.

2) Run a Global Change with the Subject Area set to activity resource assignments to clear the checkbox.

Ian


http://www.emerald-associates.com