Baseline Problem in P6

2 replies [Last post]
Mohammed Awab Ezi...
User offline. Last seen 13 years 12 weeks ago. Offline
Joined: 6 Dec 2006
Posts: 5
Groups: None
Hi everybody,

I have a little problem in assigning target to my update program When I assign previous update as a project baseline for many resoene I found all dates having Actual dates in baseline dose not appear in project baseline columns or P6 show Dates same as original baseline and sometimes same as Data_Date and
I’ve noticed all schedule percentage are wrong and calculated as per first assigned baseline!!!
In p3 everything was going Ok
Any one has answer and can help me???

Thanks and regards for ALL

Replies

Mohammed Awab Ezi...
User offline. Last seen 13 years 12 weeks ago. Offline
Joined: 6 Dec 2006
Posts: 5
Groups: None
Thanks a lot Mark ,
Really I appreciate your helping ,
Problem has been solved, your answer was correct.

Good man

Best regards

Mohammad Awab
Mark M
User offline. Last seen 14 years 24 weeks ago. Offline
Joined: 1 Jun 2008
Posts: 33
Groups: None
Greetings

If I understand your problem correctly. check your Admin Preferences; Earned Value tab;
At the bottom of that screen (under the Earned Value calculation heading) is a drop down box with 3 options, I believe yours would be set to "Budgeted values with planned dates"?
If you change this to "Budgeted values with current dates" you should get the result you’re after.

Hope that helps.

Regards
Mark