P3 V5 Project Management- Resource Curves

2 replies [Last post]
Donovan Govender
User offline. Last seen 10 years 3 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
After creating your resource curves - Histograms how do one save it and where does it save to??

Replies

Kevin Button
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
View, Layout, Save As then assign a layout name.

KB
Rodel Marasigan
User offline. Last seen 4 days 22 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Danovan,

Your query is not clear. I’m not sure if you are after on the resource curves that drive your resources profile or tracking module of P3 v5.

Resources curve are save global or default which enable you to select which curve are your going to use for each resources assigned on your activity task.

If you are after on tracking module you can save it available to all user or current user only on the tracking layout.

Hope this help.

Regards,

Rodel