Level 4 Schedule example

1 reply [Last post]
Gie Chris Rimando
User offline. Last seen 15 years 41 weeks ago. Offline
Joined: 13 Feb 2007
Posts: 7
Groups: None
Hi to all!

Can somebody send me an example of a LEVEL 4 schedule..

We have a running projects at the moment.Our client required us to submmit a level 4 schedule from our current running schedule, for them to specifically determine the problem area of our project,since we are running late already due to a lot of delays.I haven’t made such one before and i just want to see how detailed a level 4 is.

Our project is a building addition.

My e-mail add is azalea_0301@yahoo.com


Thanks for the help in advance.

Replies

James Barnes
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 6 Sep 2007
Posts: 243
I’m not sure if there’s a standard approach to numbering or describing levels of detail, but we use;

Level 1; Top level milestones - 1 A4 sheet for the project
Level 2; Phase level planning - 1 A4/A3 sheet per work area - Gives focus to phase lengths (planning, execution etc)
Level 3; Execution strategy - a few A4/A3 sheets per work area - details overall approach to the execution of the works
Level 4; Activity detail - 20k+ activities - 1 activity per man-shift
Level 5; MH calculation lines that drive the activities

This is used for Oil and Gas maintainence turnarounds, traditional building work I would say may lack level 5 completely and be of the order of one man-month per activity at level 4 (depends on your reporting period.)

I expect, though, that what your employer is demanding is one level of detail deeper than whatever you are currently providing. It is a common technique to scheudule the next 2-4 months work in a deeper level of detail than your overall plan, in your case perhaps you start the project with a level 3 plan for the whole project before you start (at tender perhaps) and then to schedule at Level 4 the works coming in the next 3 months. The term for this is "rolling wave" planning