Monitoring progress by P3.1

7 replies [Last post]
Nadim Akhtar
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 11 Oct 2004
Posts: 12
Groups: None
Dear fellows,

I m new to the scheduling world. I want to know how to compare the actual progress vs target (baseline).

I will be grateful for the help

Best regards

Nadim Akhtar

Replies

Nadim Akhtar
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 11 Oct 2004
Posts: 12
Groups: None
Thx everyone for your help.

Best regards

Nadim
Mohammed Azharuddin
User offline. Last seen 15 years 36 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 17
Nadim,

You can update the target to get the %. I have been practicing this for long time and its working.The updated Target used can be target2 which will be used only for computations. whereas the undisturbed target can be retained for other purpose.

Cheers,
Azza
Damien Galllagher
User offline. Last seen 9 years 3 days ago. Offline
Joined: 18 Apr 2007
Posts: 7
Groups: None
Nadim,

Primavera have the solution to your query, it is titled - ’How to show Planned Percent Complete (PCT) in a project based on Target dates’. If you register with Primavera POINT, you should be able to find the solution, the solution ID is 1999413102022.
This should resolve your query.

Regards,

Damien
Nadim Akhtar
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 11 Oct 2004
Posts: 12
Groups: None
Thx for your response, I actually want to compare the %age complete of actual vs target (Baseline). I have a column of actual % complete and another for target % complete.

The target (Baseline) is having a schedule date of project start. People told me that I should not update baseline. But if i dont update the baseline how I can get the planned %age as per the baseline schedule.

I m not sure if i express myself properly.

Best regards
A D
User offline. Last seen 4 years 47 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
First of all copy the project and then set target (Tools--> Project Utilities --> Targets) the baseline program.

Apply actuals by putting in the actual start, % completion and if its 100% complete, then Actual finish date.

Schedule it by pressing F9. Various options are available for scheduling. Go to Tools --> Schedule and click options.

Also, dont forget to Re-organise after scheduling.

Go to Columns area and then add Target1 early start and Target1 early finish.

Can add VARIANCE Column to check variance.

Go to Bars and then add Target1 bar.

Cheers,

Rav
Larry Rino
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 25 Oct 2007
Posts: 64
Nadim,

Additional to the latest reply, do not forget to show the baseline bars (in the View/ Bars - options) and consider different row for baseline bars and format as well (as you like), for better visibility and comparison.

Hope these helps.
Anoon Iimos
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
apply actuals and run your schedule, then compare it with your Target...