Steps in planning using primavera

2 replies [Last post]
Ranganathan Ranga...
User offline. Last seen 17 years 34 weeks ago. Offline
Joined: 9 Aug 2007
Posts: 16
I am new to primavera, can some one correct me the steps for planning if i am wrong

1.create a file using file name
2,create WBS directory using.................
3.create Resource Directory................
4 create Activity ID,Description using.....
5.Allot duration using.....
6.Allot estimated labour hours using......


please fill in the blanks like drawings/Engineering work note

tks n rgs


Ranganathan

Replies

Manuel Parra Pala...
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 7 Dec 2007
Posts: 24
I agree Raviraj. The first is to "know" the project as deep as to break in small pieces and after it is very important to know all the logical relationships, linkages, and constrains.

For me these are the harder parts and where the real job of the planner takes site.

After introducing all tasks, precedence relationship, duration analysis, based or not on bill of quantities, the proper analysis of the planning must answer what we "Know" from the very start. In other words the critical path must be the logical one.

I do not work always with resources, i mean in Primavera, but this analysis, a debt in every updating, is the basis of the planning work.

"In times of war maybe a plan can not be useful but a planning is essential". Dwight Eisenhower.
A D
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
This is not at all enough, but to be in sequence, this is it:

1. create a file using file name
2. Enter the WBS Directory in P3 from the WBS produced.
3. Enter the resources from the standard respource pool or project specific resource pool allocated.
4. Enter the Activity codes.
5. Decide the activity ID’s to be allocated depenmding upon zone / trade / contractor and others
6. Enter the activity id with description with appropriate activity codes
7. Allocate the duration and resources using the company’s standard.
8. MOST IMPORTANT - Sequence the activities in a logical manner

May be, other guys can add bit more

Cheers,

Rav