cost control

1 reply [Last post]
forat faris
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 28
Groups: None
dear all
when some activities canceled in the project ...I input the pc%=100%..
but cost report which i generate in p3 will not reflect the real picture .
HOW WE CAN REFLECT REAL COST SITUATION IN P3?
THANKS

Replies

Ife Olyke
User offline. Last seen 11 years 1 week ago. Offline
Joined: 6 Feb 2007
Posts: 147
Hi Forat,

I will not input pc% = 100% for an activity if it’s cancelled. I’d rather create a planning level for cancelled activities and apply it to activities i want to cancel. Then in the cost report format, I will add a selection criteria to exclude all cancelled acitivities. Hope this helps..Maybe someone else will have a better idea. Cheers..

Ifeanyi