achievable schedule???

3 replies [Last post]
AALAP PAREKH
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 13 Nov 2005
Posts: 9
hi all
after assigning activity scheduled early start .finish.
wat r the things which need to checked to ensure that the schedule is achievable??
thx
aalap_parekh@rediffmail.com

Replies

Zhang Haixiang
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
to use informaker, you need install ODBC driver and config data source,then you can open your project in informaker for reporting.

there are lots of threads about link MS-Access with P3,
MS-access is more easy and powerful than informaker.
In most case, export to excel is enough, if this does not work, try Access. No need to learn informaker.
AALAP PAREKH
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 13 Nov 2005
Posts: 9
hi
1) can u one tell me how infomakes useful 2 us?
i don wats it? thnk its link???m confused

Zhang Haixiang
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
first set the start date of the project,
then assign duration for each activity
then link all acvities with relationship.
P3 will caculate ES,EF for you.

If the duration and relationship is reasonable based on your resource availability, then the schedule is achievable.